Blackham TSF

TSF & Ponds Project: Blackham Resources (Wiluna WA)

Cape was contracted to:

  • Load & Haul 775,000m3 of material to build the TSF J Stage 1A/1B
  • Decommissioning of monitoring bores
  • Re-location of existing tailings and waste stockpiles
  • Excavation of selected materials from designated borrow areas and stockpiles located within existing waste dumps, placed and spread to the design lines and grades
  • Preparation of the embankment footprint area for the TSF embankment construction and TSF basin area
  • Construction of an underdrainage system and decant tower
  • Construction of a zoned earthfill embankment including the upstream toe drain.
  • Construction of a containment trench for the tailings delivery and decant return pipelines.
  • Survey settlement pins
tsf project

Project Details

Client. Blackham Resources
Location. Matilda Gold Mine, Wiluna WA, Australia
Project Duration. 8 Months