Mt Morgan Gas Pipeline

Gas Project: Dacian Gold (Laverton WA)

The Cape team completed 2.5km of trenching with 600 cubic meters of pipe bedding and backfilling to allow the installation of a 150mm steel gas main at Dacian Gold’s Mt Morgan Mine 20km West of Laverton.

The trenching was completed in three days whilst the backfilling was completed in two days, which was a cost effective and efficient solution for our client.

mt morgan project

Project Details

Client. Dacian Gold
Location. Laverton Western Australia, Australia
Project Duration. 5 Days